Sprint 8: Refactoring and bug fixing

Ticket Id

Summary

Backlog item

Assigned to

Estimation

Actual

Type

PPS-90

JSON format DSL fix

DSL fix

Giovanni Antonioni

5h

5h

Fix

PPS-86

Implement scrape tests

DSL test

Giovanni Antonioni

4h

4h

Test

PPS-80

Spawn entities anonymously

Actor implementation

Giovanni Antonioni

2h

2h 30m

Fix

PPS-81

Remove rules

Utilities refactoring

Giovanni Antonioni

10m

10m

Refactoring

PPS-72

Implement Ruling keywords in the DSL

DSL

Giovanni Antonioni

2h

2h

Dev

PPS-97

Implement test of whole application

Test

Luca Rubboli

3h

3h

Test

PPS-116

Fix Robot.txt

Enhancement

Francesco Magnani

30m

2h

Fix

PPS-98

Build the fat JAR

CI

Francesco Magnani

30m

1h 30m

Configuration

PPS-78

Implement safety mechanisms for DSL usage

DSL

Francesco Magnani

3h

2h

Enhancement

PPS-88

Implement ScoobyTest

Test

Francesco Magnani

1h

1h

Test

PPS-82

Remove compilation warnings

Enhancement

Valerio Di Zio, Luca Rubboli

1h

1h

Fix

PPS-75

Check and refactoring

Enhancement

Giovanni Antonioni, Valerio Di Zio, Luca Rubboli, Francesco Magnani

4h

4h

Refactoring

PPS-74

Implement Headers logic in DSL

DSL

Valerio Di Zio

3h 30m

5h

Dev

PPS-56

clean up your code before dsl

Enhancement

Giovanni Antonioni, Valerio Di Zio, Luca Rubboli, Francesco Magnani

3h

3h 30m

Refactoring

PPS-92

Remove some warning inside code

Enhancement

Valerio Di Zio

1h

1h

Refactoring

PPS-91

Unused import removal

Enhancement

Valerio Di Zio

1h

1h

Refactoring

PPS-120

Apply export refactor and scraper refactor

Enhancement

Luca Rubboli

1h

1h

Refactoring

PPS-85

Implement crawl tests

DSL test

Valerio Di Zio

2h

2h

Test

PPS-79

Implement HTML element method "parent"

Document library

Francesco Magnani

30m

30m

Enhancement

PPS-84

Implement exporter tests

DSL test

Luca Rubboli

7h

6h

Test

PPS-87

Implement config tests

DSL test

Francesco Magnani

1h

1h

Test

PPS-89

Scooby termination fix

Actor orchestration

Francesco Magnani

30m

2h

Fix

PPS-73

Implement Export keywords in the DSL

DSL

Luca Rubboli

1d

1d 2h

Dev

Sprint goal

Goals of this sprint:

  • Code clean-up and refactoring;

  • DSL application test against standard configuration and application usage in common websites;

  • Arising bug fixing;

  • DSL refinements;

  • Fat JAR build.

Sprint deadline

28/07/2024

Sprint review

All tasks but exception management of actors execution has been completed. All bugs arisen from application's test usage have been promptly fixed due to clean code. Some DSL refinements in backlog took a bit of time.

Sprint retrospective

Given the variety of bugs arisen from application usage, this sprint focused on bug fixing and application usage. The most challenging part was about setting-up the wider variety of edge cases possible.