Sprint 2 : Initial setup and prototyping

Ticket Id

Summary

Backlog Item

Assigned to

Estimation

Actual

Type

PPS-19

Scraper prototyping

Domain prototyping

Luca Rubboli

4h

1h

Design

PPS-23

Launch Cucumber tests from sbt command line

Project configuration

Giovanni Antonioni

10m

10m

Enhancement

PPS-20

Crawler prototyping

Domain prototyping

Giovanni Antonioni, Francesco Magnani

30m

45m

Design

PPS-14

Define Cucumber tests: Scraper

Cucumber test definition

Luca Rubboli

4h

3h

Test

PPS-17

Define Cucumber tests: Coordinator

Cucumber test definition

Valerio Di Zio

4h

3h

Test

PPS-16

Define Cucumber tests: Exporter

Cucumber test definition

Francesco Magnani

3h

3h

Test

PPS-15

Define Cucumber tests: Crawler

Cucumber test definition

Giovanni Antonioni

1h

1h

Test

PPS-13

Configure repository of the Project

Project configuration

Giovanni Antonioni

1h 30m

1h

Configuration

Sprint goal

  • Setting up the project environment and all the development tools needed;

  • Write a simple prototype of the main entities of the project.

Sprint deadline

16/06/2024

Sprint review

The tasks were completed on time and no tasks were left behind. A simple prototype of the main entities is ready and can be taken as a starting point for the next sprints.

Sprint retrospective

We've overstimated the time needed for complete the task, in particular, for cucumber tests definition. This is due to the fact that the team is not yet familiar with the tools and the technologies used in the project, and we've counted also the time needed to learn them.